Temelín Nuclear Power Station Explained

Temelín Nuclear Power Station
Country:Czech Republic
Location:Temelín, South Bohemian Region
Coordinates:49.1801°N 14.3762°W
Operator:ČEZ Group
Employees:~1,000
Construction Began:1981
Commissioned:10 June 2002
Np Reactor Type:VVER 1000/320 PWRs
Ps Units Operational:2 x 1080 MWe (gross)[1] [2]
Ps Units Cancelled:2 x 950 MWe
Ps Annual Generation:14,401 GWh
Ps Electrical Cap Fac:80.0%
Status:O
Cost:98.6 billion CZK

Temelín Nuclear Power Station (cs|Jaderná elektrárna Temelín, abbreviation ETE) is a nuclear power plant in Temelín, Czech Republic. It is owned by ČEZ Group, which employs 1,000 workers at the site. The adjacent castle Vysoký Hrádek serves as an information centre.

In 2003, the Temelín Nuclear Power Plant, with its 2,180 MW of installed capacity, became the largest power resource in the Czech Republic and the largest source of zero-emission electricity generation by far.[3] [4]

History

Planning for the Temelín Nuclear Power Station began in the late 1970s, and the final project was submitted in 1985. Construction of four operating units began in 1987. The project was expected to be completed in 1991, with estimated building costs of 35 billion CSK.[5] Six villages were demolished by the then-Communist government to make way for the power station.[6]

After the Velvet Revolution in 1990, the Czechoslovak government decided to cease construction of the third and fourth reactors;[7] work continued on the first two reactors, however. In the 1990s, alterations to the original design were made by Westinghouse, in conjunction with SUJB and the IAEA, to bring reliability and safety levels into conformance with Western European standards. The standards audit was carried out by Halliburton NUS. As part of the alterations, information and control systems were added, electrical modifications carried out, and cabling, reactor core, and fuel elements were replaced.[8] In 1993, the Czech government decided to complete the plant in the face of delays and cost overruns, with expected completion at the time estimated for 1997.[9] In 1994, an opinion poll reported that 68% of Czech citizens were in favour of nuclear power development.[10]

By 1998, construction was still not completed, and costs reached 71 billion CZK. The Czech government again reconsidered completion of the plant.[11] In 1999, the decision was made to continue, projecting completion to 2000, with a maximum cost of 98.6 CZK billion.[12] The project was controversial; national and international (mainly Austrian) opposition was stronger than in the early 1990s, and public opinion on the project fluctuated. In a 1999 opinion poll, 47% of Czech citizens were in favour and 53% against nuclear power development, a fall from 1994. In subsequent years, the same poll showed 63% in favour and 37% against in 2000 and 58% in favour and 42% against in 2001.[10]

In September and October 2000, Austrian anti-nuclear protesters demonstrated against the Temelín Nuclear Power Plant and at one stage temporarily blocked all 26 border crossings between Austria and the Czech Republic.[13] [14]

As a result of cost overruns, political changes, and design changes to the plant, reactor 1 began commercial operations in June 2002, and reactor 2 on 18 April 2003. As of 2023, the two reactors had produced 272 TWh, or 272.000.000.000 kWh of electricity, with no CO2 emissions. [15] Assuming a price level of CZK 2 per kWh, this amounted to 544 billion CZK. As the initial investment was CZK 100 billion, the plant had turned a profit. In 2022 alone, the operators of the plant earned CZK 80 billion, as a result of the Russian invasion of Ukraine and the resulting energy crisis.[16]

Melk Protocol

The Melk Protocol, signed on 12 December 2000 in Melk, Austria, is the result of negotiations between the Czech and Austrian governments, led by Czech prime minister Miloš Zeman and Austrian chancellor Wolfgang Schüssel, with the participation of European Commissioner Günter Verheugen.[17] The aim of the protocol was to resolve disputes over the Temelín plant, with Austria raising several concerns about its safety and procedures.[18] The Czech Republic committed itself to some above-standard procedures (e.g., notification of events at Temelín to Austria, and a more stringent environmental impact assessment). Consequently, Austria recognised the importance of EU enlargement and agreed that the free movement of goods and people must be preserved (this clause was a response to the blockade of Czech–Austrian border crossings by Austrian anti-nuclear activists). The protocol is not legally binding.[19]

Technical data

In 2013, the reactors were uprated from 3,000 MW thermal output to 3,120 MW, bringing the total output to 1,003 MWe net and 1,056 MWe gross.[20] [21] [22] In 2015, turbomachinery was updated, bringing total output to the current 1,026 MWe net and 1,080 MWe gross.[23]

Station Reactor type Net capacity[24] Gross capacity Thermal output Initial criticality Grid date Exp. shutdown
Temelín 1VVER 1000 type V 320 PW1,080 MWe 3,120 MW Dec 2000Jun 20022062
Temelín 2VVER 1000 type V 320 PW1,026 MWe 1,080 MWe 3,120 MW Dec 2002Apr 20032063[25]

Reactor vessel (core)

Reactor cooling system

Steam generator

Cooling circuit

Protective envelope (containment)

Turbine generator set

Reliability

IAEA data show that reactor 1 reaches a cumulative operating factor of about 63%,[26] and reactor 2 of about 76%.[27] The cumulative operating factor figures for Temelín NPP reactors are lower than the figures of similar reactors operated in Russia, where it is around 80–87%.[28] [29]

ČEZ has increased the operating factor as well as production in recent years, and the plant reached 84% in 2012, with a total record production of 15 TWh.[30]

New reactors

Plans to build all four original reactors were reopened in 2005. However, in 2014, the prospective plans were cancelled.

In 2007, planning was suspended because the incoming government agreed not to promote nuclear energy. However, in July 2008, ČEZ requested the Ministry of the Environment conduct an environmental impact assessment for two additional reactors.[31] In 2009, regional approval was granted for the new build. In August 2009, ČEZ sought bids for two pressurized water reactors.[32] Shortly after the Fukushima nuclear accident, prime minister Petr Nečas announced that the construction of new reactors would continue according to original plans[33] but with the tender selection delayed until 2013.[34]

In July 2012, ČEZ opened public-contract bids for completing the Temelín Nuclear Power Plant in the presence of the bidders—Areva; a consortium of the Westinghouse Electric Company; and a consortium of ŠKODA JS, Atomstroyexport, and Gidropress.[35] In October 2012, Areva's bid was excluded from further evaluation, as they had not met statutory requirements.[36]

In March 2013, a Russian-led consortium, comprising Atomstroyexport, Gidropress, and Škoda, signed contracts with the Czech companies ZAT, Hochtief CZ, and UJV Rez, for the construction of two new nuclear reactor units for Temelín-3 and Temelín-4, both of which being MIR-1200 (Modernised International Reactor). ZAT would supply automated systems for the plant, Hochtief CZ would be responsible for construction of the nuclear island, and UJV Rez would help compile project documentation for the nuclear and turbine islands and also create working documentation for construction of the plant. A statement said the consortium was aiming for a "localisation level" of 75 percent. The other running project for the contract was Westinghouse, with its AP1000 reactor. The winner of the contract was scheduled to be announced at the end of 2013.[37]

In April 2014, ČEZ cancelled the project after the Czech government stated it did not plan to provide guarantees or other mechanisms to support the construction of low-emission power plants following discussions in the EU. The ČEZ CEO stated:

In 2021, Westinghouse was contracted to upgrade the instrumentation and control systems of the power plant in a nine-year project.[38]

See also

External links

Notes and References

  1. Web site: 8 May 2018. PRIS - Reactor Details. iaea.org. https://web.archive.org/web/20180508185611/https://www.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=74. 8 May 2018. live.
  2. Web site: 8 May 2018. PRIS - Reactor Details. iaea.org. https://web.archive.org/web/20180508185704/https://www.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=75. 8 May 2018. live.
  3. Web site: CEZ Group | Temelín . Cez.cz . 7 March 2014 . https://web.archive.org/web/20101225010614/http://www.cez.cz/en/power-plants-and-environment/nuclear-power-plants/temelin.html . 25 December 2010 . live.
  4. Web site: Decarbonization | Sustainability in CEZ Group .
  5. Web site: Temelin nuclear power plant activated. Czech Radio. 12 October 2000. 8 February 2023.
  6. Web site: Economic, social and environmental impact of building and functioning of the nuclear power plants Temelín on Southern Bohemia . Theses.cz . 4 December 2011 . https://web.archive.org/web/20111008222150/http://theses.cz/id/5hf8le/ . 8 October 2011 . live.
  7. Web site: Ekolist: Historie výstavby Jaderné elektrárny Temelín . 10 November 2006 . Ekolist.cz . 4 December 2011 . https://web.archive.org/web/20080329091918/http://www.ekolist.cz/zprava.shtml?x=1932667 . 29 March 2008 . live.
  8. News: Temelin NPP Status: The Challenge of Safety Improvements. The Uranium Institute. 31 December 2000. 3 August 2009. https://web.archive.org/web/20090408172315/http://www.world-nuclear.org/sym/2000/hezoucky.htm. 8 April 2009. live.
  9. Web site: Usnesení vlády České republiky ze dne 10. března 1993 č. 109 k problematice dostavby jaderné elektrárny Temelín . Kormoran.vlada.cz . 10 March 1993 . 4 December 2011 . https://web.archive.org/web/20120303145243/http://kormoran.vlada.cz/usneseni/usneseni_webtest.nsf/WebGovRes/6925AD93BE283D82C12571B6006FCE61?OpenDocument . 3 March 2012 . live.
  10. Web site: Rozvoj jaderné energetiky u nás podporují necelé tři pětiny občanů . Stem.cz . 4 December 2011 . https://web.archive.org/web/20120303145242/http://www.stem.cz/clanek/111 . 3 March 2012 . live.
  11. Web site: Usnesení vlády České republiky ze dne 12. srpna 1998 č. 516 o postupu nezávislého posouzení projektu dostavby jaderné elektrárny Temelín . Kormoran.vlada.cz . 12 August 1998 . 4 December 2011 . https://web.archive.org/web/20120303145248/http://kormoran.vlada.cz/usneseni/usneseni_webtest.nsf/WebGovRes/2C601D0777983566C12571B6006BD92C?OpenDocument . 3 March 2012 . live.
  12. Web site: Usnesení vlády České republiky ze dne 12. května 1999 č. 472 k návrhu postupu řešení situace jaderné elektrárny Temelín . Kormoran.vlada.cz . 12 May 1999 . 4 December 2011 . https://web.archive.org/web/20120303145256/http://kormoran.vlada.cz/usneseni/usneseni_webtest.nsf/WebGovRes/7038A0CA78622833C12571B6006D3428?OpenDocument . 3 March 2012 . live.
  13. News: Anti-nuclear protest on Czech border . BBC News . 15 September 2000 . 4 December 2011 . https://web.archive.org/web/20140202223229/http://news.bbc.co.uk/2/hi/europe/926434.stm . 2 February 2014 . live.
  14. News: Austrian anti-nuclear protests continue . BBC News . 14 October 2000 . 4 December 2011 . https://web.archive.org/web/20140202223226/http://news.bbc.co.uk/2/hi/europe/963826.stm . 2 February 2014 . live.
  15. Web site: PRIS – Country Details .
  16. Web site: ČEZ Group earned over CZK 80 billion in 2022, will pay more than CZK 100 billion to the Czech State this year .
  17. Web site: P-1775/2006 . 19 May 2006 . European Parliament . . 4 March 2022 . "The Melk Protocol is a bilateral agreement which was signed on 12 December 2000 by the Czech Prime Minister and the Austrian Chancellor. The Commission was present, offering its good offices to mediate between both parties. The Melk Process was followed up by a meeting of the Czech Prime Minister, the Austrian chancellor and the commission on 29 November 2001, where 'conclusions of Melk Process and follow-up' were signed by both parties (so-called Brussels Protocol).".
  18. Web site: P-1775/2006 . 19 May 2006 . European Parliament . . 4 March 2022 . "The role of the Commission in the mediation process leading up to the Protocol was not to evaluate the technical safety of the Temelin power plant, but rather one of a political nature, to facilitate the dialogue and exchange of information between Austria and the Czech Republic, in order to both identify the main issues of concern and to find solutions to the problems which were identified. Procedures were agreed bilaterally in order to follow up the implementation of improvements which might take more time to be completed. The subsequent monitoring of the Melk provisions, extended to the public, is considered as a model of bilateral transparency.".
  19. Web site: ČR a Rakousko uzavřely proces z Melku . 30 November 2001 . Radio Prague International . Faltýnek . Vilém . 4 March 2022 . "Verheugen oznámil, že Evropská komise hned v pátek předloží členským státům návrh společné pozice vůči ČR v kapitole energetika s doporučením ji uzavřít. Rakouská strana se zavázala, že tomu nebude bránit.".
  20. Web site: CEZ Group | Temelín . Cez.cz . 4 December 2011 . https://web.archive.org/web/20120124082234/http://www.cez.cz/en/power-plants-and-environment/nuclear-power-plants/temelin.html . 24 January 2012 . live.
  21. Web site: PRIS – Czech Republic . IAEA . 15 September 2014 . https://web.archive.org/web/20150509175542/http://www.iaea.org/PRIS/CountryStatistics/ReactorDetails.aspx?current=74 . 9 May 2015 . live.
  22. Web site: Temelín Power Update. Bica. Martin. Nov 2013. https://web.archive.org/web/20180508185438/http://ftp.vver2013.com/VVER%202013%20-%20Day%20II.,%20Parallel%20Section%20I.,%20PDF/Bica%20M.%20-%20presentation%202.pdf. 8 May 2018. live.
  23. News: Temelín reaguje na horko připojením čtyř chladicích věží k prvnímu bloku. 21 July 2016. OEnergetice.cz. 8 May 2018. cs. https://web.archive.org/web/20180509012452/http://oenergetice.cz/jaderne-elektrarny/temelin-pripojil-k-prvnimu-bloku-ctyri-chladici-veze/. 9 May 2018. live.
  24. Web site: Czech Republic: Nuclear Power Reactors – Alphabetic . IAEA . 4 December 2011 . dead . https://web.archive.org/web/20110604091232/http://www.iaea.org/cgi-bin/db.page.pl/pris.powrea.htm?country=CZ&sort=&sortlong=Alphabetic . 4 June 2011.
  25. Web site: Temelín 2 clear for longer operation: Regulation & Safety – World Nuclear News.
  26. Web site: PRIS.Contact-Point@iaea.org . Temelin Reactor 1 at PRIS . Iaea.org . 4 December 2011 .
  27. Web site: PRIS.Contact-Point@iaea.org . Temelin Reactor 2 at PRIS . Iaea.org . 4 December 2011 .
  28. http://www.iaea.org/cgi-bin/db.page.pl/pris.ophis.htm?country=RU&site=VOLGODONSK&units=&refno=59&opyear=2010&link=HOT Rostov Reactor 1
  29. http://www.iaea.org/cgi-bin/db.page.pl/pris.ophis.htm?country=RU&site=KALININ&units=&refno=36&opyear=2010&link=HOT Kalinin Reactor 3
  30. Web site: Temelín vyrobil v roce 2012 rekordní množství elektřiny . 12 January 2013 . https://web.archive.org/web/20130121160301/http://www.cez.cz/cs/pro-media/aktuality-z-jadernych-elektraren/11689.html . 21 January 2013 . live.
  31. News: CEZ requests EIA for expansion of Temelin. World Nuclear News. 14 July 2008. 9 August 2008. https://web.archive.org/web/20090105223758/http://www.world-nuclear-news.org/NN-CEZ_requests_EIA_for_expansion_of_Temelin-1407084.html. 5 January 2009. live.
  32. News: Tender launched for Temelin expansion . 3 August 2009 . World Nuclear News . 3 August 2009 . https://web.archive.org/web/20091101060633/http://www.world-nuclear-news.org/NN-Tender_launched_for_Temelin_expansion-0308094.html. 1 November 2009 . live.
  33. Web site: jw . Temelín dostavíme, vzkázal po havárii Fukušimy premiér Nečas – iDNES.cz . Mladá fronta DNES . 17 March 2011 . 4 December 2011 . https://web.archive.org/web/20110322092146/http://zpravy.idnes.cz/temelin-dostavime-vzkazal-po-havarii-fukusimy-premier-necas-p5e-/domaci.asp?c=A110317_144606_domaci_jw . 22 March 2011 . live.
  34. News: ČEZ delays Temelín completion deadline by 5 yrs to 2025 . 21 February 2011 . Prague Daily Monitor . 23 September 2011 . https://web.archive.org/web/20120326015901/http://praguemonitor.com/2011/02/21/%C4%8Dez-delays-temel%C3%ADn-completion-deadline-5-yrs-2025 . 26 March 2012 . dead .
  35. Web site: CEZ Group | ČEZ Has Today Opened Bids from Three Qualified Bidders Interested in Completing the Temelín NPP and have Thus Started the Bid Evaluation Process . Cez.cz . 7 March 2014 . https://web.archive.org/web/20121102133950/http://www.cez.cz/en/cez-group/media/press-releases/3867.html . 2 November 2012 . live.
  36. Web site: CEZ Group | Areva Failed to Comply with Public Contract Requirements Defined for Building Temelín NPP Units 3 and 4; ČEZ Had to Disqualify This Bidder . Cez.cz . 17 January 2014 . 7 March 2014 . https://web.archive.org/web/20121101040855/http://www.cez.cz/en/cez-group/media/press-releases/3972.html . 1 November 2012 . live.
  37. Web site: MIR-1200 Consortium Signs Temelín Contracts With Czech Companies . Nucnet.org . 2 July 2012 . 7 March 2014 . https://web.archive.org/web/20131019090015/http://www.nucnet.org/all-the-news/2013/03/15/mir-1200-consortium-signs-temel-n-contracts-with-czech-companies . 19 October 2013 . live.
  38. News: Westinghouse to upgrade Temelin NPP's I&C systems . Nuclear Engineering International . 16 September 2021 . 22 September 2021.