Rusumo Hydroelectric Power Station Explained

Rusumo Hydroelectric Power Station
Name Official:Urugomero rw'amashanyarazi rwa Rusumo
Centrale hydroélectrique de Rusumo
Location Map:Rwanda
Location Map Caption:Map of Rwanda showing the location of
Rusumo Falls
Coordinates:-2.3797°N 30.7858°W
Country:Rwanda
Location:Rusumo Falls, Kirehe District
Purpose:P
Status:O
Construction Began:2017
Opening:2024[1]
Cost:US$468 million
Operator:Rusumo Power Company Limited
Dam Crosses:Kagera River
Res Elevation:1325m (4,347feet)
Plant Commission:2023 (expected)
Plant Type:R
Plant Turbines:3
Plant Capacity:80MW

The Rusumo Hydroelectric Power Station (rw|Urugomero rw'amashanyarazi rwa Rusumo, fr|Centrale hydroélectrique de Rusumo), also known as the Rusumo Power Station, is an operational hydropower plant, with initial capacity installation of . The project involved the construction of a dam, with run of river design. A more expensive reservoir design was considered before being abandoned in favor of an 80 MW project with a smaller environmental impact and an estimated cost of US$300 million compared to US$400 million for the bigger project.[2]

The World Bank announced on 6 August 2013 that it had approved loans totaling US$340 million towards the US$468.60 million needed for the project.[3] In November 2013, the African Development Bank approved a loan of US$113 million towards completion of the project.[4] [5]

Location

The power station is on the Kagera River, along Rwanda's border with Tanzania and approximately 2km (01miles) downstream of the tripoint where the two countries share a common border with Burundi. The project is sited at Rusumo Falls, near the town of Rusumo, approximately, by road, southeast of Kigali, the capital and largest city of Rwanda. Rusumo Falls is approximately, by road, south-east of the provincial headquarters at Kibungo, in Ngoma District. The approximate coordinates of the power station are: 02°22'47.0"S, 30°47'09.0"E (Latitude:-2.379722; Longitude:30.785833).

Other considerations

The power generated will be shared equally among the countries of Burundi, Rwanda, and Tanzania.[4] The power will be evacuated from the generation plant via 220 kilovolt transmission lines to transmission stations in: Gitega, Burundi, a distance of ; Kigali, Rwanda, a distance of ; and, Nyakanazi, Tanzania, a distance of .[6]

Developments

In November 2016, two contracts that paved the way for construction of the power station were signed in Kigali, Rwanda. The first contract was between Rusumo Power Company Limited and a consortium of contractors that included a joint venture composed of CGCOC Group Limited and Jiangxi Water & Hydropower Construction Company Limited. This contract provides for the performance of civil works, including supply and installation of hydro-mechanical equipment.

The second contract was signed between Rusumo Power Company Limited and a consortium of companies, including Rusumo Falls Andritz Hydro GmbH of Germany and Andritz Hydro PVT Limited of India, to carry out electrical and mechanical works for power generation.[7]

As of November 2016, the projected cost of the project is $340 million, to be financed by The World Bank. The three high voltage transmission lines that will evacuate the power generated are projected to cost $121 million, financed by the African Development Bank. Construction is planned to begin in January 2017.[7]

Construction

The ground-breaking ceremony was held at Ngara, in Tanzanian territory on 30 March 2017, attended by government officials from the three beneficiary countries; all members of the regional East African Community. The power station is owned by Rusumo Power Company Limited (RPCL), a special purpose vehicle company, owned by the three countries.[8] Two contractors were selected for the project. A Joint Venture between CGCOC Group and Jiangxi Water & Hydropower Construction Company Limited is responsible for the civil works, while ANDRITZ Hydro from Germany and India are responsible for the electro-mechanical works.[8]

The Coordination Unit of the Nile Equatorial Lakes Subsidiary Action Program (NELSAP-CU), is implementing the project on behalf of the owners. Completion and commercial commissioning were expected in 2020.[8]

Construction work on this project was estimated at 35 percent as of February 2019, and 59 percent as of January 2020.[9]

As of April 2021, completion was anticipated in 2022, with one of the three power-generating units expected online in the fourth quarter of 2021.[10]

As of June 2021, with 80 percent of the work completed, commercial commissioning was anticipated in December 2021.[11]

Audits by the Auditor Generals of the three affected countries, carried out in the second half of 2021, have revealed a 22 percent increase in expenditure, up to that point in the work plan, above what was budgeted. At that time work completion was estimated at 81 percent.[12] As of August 2022, an estimated 95 percent of the work was complete. Completion is anticipated in November 2022, with commercial commissioning in December 2022.[13] Later that month, commercial communication was pushed back to the first quarter of 2023.[14]

Completion and commercial commissioning were achieved in H1 2024.[1] [15]

See also

External links

Notes and References

  1. Web site: . Tanzania, Burundi, Rwanda's power plant handover set for April . 14 February 2024 . Josephine Christopher . 14 October 2024 . Dar es Salaam, Tanzania.
  2. Web site: Rusumo Hydropower To Generate 80MW . 12 March 2012 . . Edwin Musoni . 8 April 2016 . Kigali, Rwanda.
  3. Web site: World Bank Approves Rusumo Falls Hydropower Plant . . 6 August 2013 . 18 February 2015 . Washington, DC, United States.
  4. Web site: 27 November 2013 . 18 February 2015 . Rwanda's 80 Megawatt Rusumo Falls Hydropower Project Receives $113 Million . Hydroworld.com.
  5. Web site: AfDB Board Commits US$113 Million to Regional Rusumo Falls Hydropower Project . 27 November 2013 . 18 February 2015 . AfDB . African Development Bank (AfDB).
  6. Web site: Rusumo Falls: Water for Power Generation And Multipurpose Use, Burundi, Rwanda, Tanzania . Icafrica.org . 2008 . 18 February 2015 . Déogratias Mbesherubusa .
  7. Web site: 15 November 2016 . Rusumo power project construction a step closer . . Diane Mushimiyimana . 11 November 2016 . Kigali, Rwanda.
  8. Web site: . Rwanda, Tanzania, Burundi start construction of Rusumo Dam . 30 March 2017 . 21 May 2018 . Kampala, Uganda.
  9. Web site: Construction Review Online . Rusumo hydroelectric power project in Tanzania now 59 percent complete . Patricia Ilolo . 13 January 2020 . 8 April 2020 . Nairobi, Kenya.
  10. Web site: Rwanda: Rusumo Power Plant Could Start Operations By End of 2021 . 19 April 2021 . . Michel Nkurunziza . 22 April 2021 . Kigali . via AllAfrica.com.
  11. Web site: East Africa: 80-Megawatt Rusumo Power Plant to Begin Electricity Supply in December . 13 June 2021 . 16 June 2021 . . Jean De Dieu Nsabimana . Kigali, Rwanda . via AllAfrica.com.
  12. Web site: 12 October 2021 . Rusumo power project delayed by two years . . Johnson Kanamugire . 12 October 2021 . Nairobi, Kenya.
  13. Web site: . 22 August 2022 . Joint Tanzania, Burundi and Rwanda power project nears completion . The Citizen, Tanzania . 25 August 2022 . Nairobi, Kenya . The EastAfrican Quoting The Citizen (Tanzania).
  14. Web site: 28 August 2022 . Rusumo power 'to reach grid by March' . . Ange Iliza . 29 August 2022 . Nairobi, Kenya.
  15. Web site: Rusumo hydropower project transforms lives in Burundi and its neighbours . . 7 October 2024 . 14 October 2024 . Kampala, Uganda.