Granville Harbour Wind Farm | |
Coordinates: | -41.802°N 145.056°W |
Country: | Australia |
Location: | Zeehan, Tasmania |
Status: | O |
Construction Began: | August 2018 |
Commissioned: | December 2020 |
Cost: | $280 million |
Operator: | Palisade Investment Partners |
Ps Units Operational: | 31 × 3.6 MW |
Ps Units Manu Model: | Vestas V126 |
Wind Hub Height: | 137m (449feet) |
Wind Rotor Diameter: | 126m (413feet) |
Wind Farm Type: | Onshore |
Ps Electrical Capacity: | 112 MW |
Ps Electrical Cap Fac: | 41.63% (2021) |
Ps Annual Generation: | 408.5 GWh (2021) |
Granville Harbour Wind Farm is a wind farm operated by Palisade Investment Partners, on the west coast of Tasmania, Australia.
The facility first generated to the grid on 27 February 2020 with the completion of its first turbine, with the site being fully commissioned and operational in December 2020.[1] The wind farm has 31 wind turbines and have a maximum capacity of 112 MW.[2]
It is located on a site northwest of Zeehan, Tasmania.[3]
The generation table uses eljmkt nemlog to obtain generation values for each month. Grid connection started in January 2020, and was fully commissioned in December 2020.
2020 | 216,847 | 0* | 704* | 5,265* | 11,461* | 22,341* | 29,220* | 23,440* | 78* | 35,447* | 22,415* | 30,988* | 35,488* | |
2021 | 408,465 | 29,023 | 24,288 | 28,624 | 33,850 | 41,981 | 31,432 | 41,395 | 47,711 | 39,424 | 38,754 | 24,846 | 27,137 |