Gitaru Hydroelectric Power Station | |
Location Map: | Kenya |
Country: | Kenya |
Location: | Embu County/Machakos County |
Coordinates: | -0.7953°N 37.7525°W |
Owner: | Kenya Electricity Generating Company |
Purpose: | Power |
Status: | O |
Construction Began: | 1975 |
Dam Type: | reservoir |
Dam Crosses: | Tana River |
Dam Length: | 580m (1,900feet) |
Dam Height: | 30m (100feet) |
Spillway Capacity: | 4500m3/s |
Res Capacity Total: | 16000000m2 |
Res Elevation: | 924m (3,031feet) |
Plant Name: | Gitaru Hydroelectric Power Station |
Plant Coordinates: | -0.7953°N 37.7525°W |
Plant Operator: | Kenya Electricity Generating Company |
Plant Type: | R |
Plant Hydraulic Head: | 136m (446feet) |
Plant Turbines: | 2 x 72 MW, 1 x 81 MW Francis-type |
Plant Capacity: | 225MW |
Plant Commission: | 1999 (Unit 3) |
The Gitaru Hydroelectric Power Station, also known as the Gitaru Dam, is a rock and earth-filled embankment dam on the Tana River in Kenya. It straddles the border between Embu and Machakos Counties in the former Eastern Province. The primary purpose of the dam is hydroelectric power generation. It supports a 225 megawatt power station.[1]
The power station is located approximately 16.5km (10.3miles), by road, east of the town of Mavuria in Embu County. This is approximately 161km (100miles), by road, northeast of Nairobi, Kenya's capital city. The geographical coordinates of Gitaru Power Station are:00°47'43.0"S, 37°45'09.0"E (Latitude:-0.795278; Longitude:37.752500).
Construction of the dam began in 1975 and was completed in 1978. The third generating set, mobilizing the full potential of the power station was not commissioned until 1999.[2] The World Bank lent US$63 million towards the development of this power station. The station is operated by the Kenya Electricity Generating Company and is part of the Seven Forks Scheme.[3]
The 30m (100feet) tall dam holds a 16000000m2 reservoir. The relatively small reservoir relies on steady releases from the Masinga and Kamburu Dams upstream. The reservoir power station is located underground near the left abutment and contains two 72 megawatt and one 81 megawatt Francis turbine-generators. Water released from the station is returned to the Tana at the Kindaruma Reservoir via a 4.7km (02.9miles) long tailrace tunnel. The difference in elevation between the reservoir and power station affords a net hydraulic head of 136m (446feet).[4]