Cherry Tree Wind Farm | |
Country: | Australia |
Location: | South of Seymour, Victoria |
Coordinates: | -37.1°N 145.26°W |
Status: | Operational |
Construction Began: | January 2019 |
Commissioned: | June 2020 |
Owner: | John Laing Group |
Operator: | Vestas |
Wind Farm Type: | Onshore |
Wind Hub Height: | 910NaN0 |
Wind Rotor Diameter: | 1360NaN0 |
Wind Rated Speed: | 130NaN0 |
Ps Units Operational: | 16 × 3.6 MW |
Ps Units Manu Model: | Vestas V136 |
Ps Electrical Capacity: | 57.6 MW |
Ps Electrical Cap Fac: | 38.41% (2020-2021) |
Ps Annual Generation: | 193.8 GWh (2020-2021) |
Cherry Tree Wind Farm is a small wind farm located approximately 15 km south-east of Seymour, Victoria.[1] The 16 turbine, 57.6 MW farm was developed and constructed by Infigen Energy for John Laing Group. Construction started in January 2019 and was operational in June 2020. The wind farm is expected to generate 182 GWh on average annually, for a capacity factor of 36%.
The wind farm began grid commissioning in May 2020 and was fully commissioned in June 2020 and has operated continuously since then. The generation table uses eljmkt nemlog to obtain generation values for each month.
2020 | 121,881 | N/A | N/A | N/A | N/A | 9,082* | 8,396* | 15,778 | 16,703 | 18,441 | 18,139 | 17,074 | 18,268 | |
2021 | 18,526 | 16,223 | 15,450 | 10,556 | 14,463 | 14,179 | 15,350 | 12,655 | 12,777 |